10.1 :meet the spot
10.6 :digging the ditch for the power rerout
10.20:finally after all the permits are secured the mason is ready to dig the foundation
10.24:My guys are working hard
10.29:the layout is finished
11.3.Starting pouring the slab..
..and voila!
11.11: erecting the walls..
11.18:lumber delivery on a freezing morning.Thanks Dykes!!
11.27: first snow of the winter..Happy Thanksgiving!
12.05: first floor framing done
12.12:roof is done
12.12:roof is done